May 18-21 (10 p.m. - 6 a.m.)
- All westbound lanes and ramps of I-4 from Kirkman Road to west of S.R. 528 will be closed, except for the westbound I-4 entrance ramp from westbound S.R. 528 and the westbound I-4 exit ramp to Kirkman Road.
May 21 and 22 (10 p.m. - 6 a.m.)
- All lanes of eastbound I-4 under S.R. 528.
- The westbound I-4 exit ramp to S.R. 528 (Exit 72)
NOTE: If crews complete the westbound I-4 portion of work on the night of Monday, May 19, the closures currently scheduled for May 21-22 may be started a night early – on Tuesday night, May 20.
Lane Closures
Page 2 of 2
-
Sunday, May 18, through Thursday, May 22, from 9 p.m. to 6 a.m., motorists can expect intermittent inside and outside single lane closures on eastbound and westbound Granada Boulevard (S.R. 40) from S.R. A1A to S.R. 5. The work includes retrofit lighting, concrete removal, directional drilling, and the installation of conduit and splice boxes.
-
Friday, May 16 to Monday, March 19: Motorists should anticipate continuous lane closures in the right turn lane of westbound State Road (S.R.) 436 onto northbound S.R. 434. These closures are being done to make way for crews as they work to remove the pedestrian island, reconstruct a new pedestrian landing, and install new traffic signals.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Monday, May 19, through Friday, May 23, from 7 p.m. to 6 a.m.: Motorists should expect intermittent eastbound single outside lane closure and road closure on S.R. 50 at Fairvilla Road and Silverton Street for utility installations. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Monday, May 19, through Friday, May 23, from 7 p.m. to 6 a.m.: Motorists should expect intermittent westbound single outside lane closure and road closure on S.R. 50 at Fairvilla Road and Ferguson Drive for sidewalk work and paving. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Sunday, May 18 through Monday, May 19 from 8 p.m. to 6 a.m.: Motorists can expect northbound and southbound alternate inside and outside single lane closures on S.R. 535 from U.S. 192 to International Drive for drainage work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Monday, May 19 through Thursday, May 22 from 9:30 p.m. to 6 a.m.: Motorists should expect alternating outside single lane closures at S.R. 50 and Highland Avenue for mast arm and signalization work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Please visit, fdot.tips/alertsmap for the latest information on lane closures and announcements.
-
Beginning Tuesday, May 13, there will be detours for Spring Garden Ranch Road. The closure, located on the west end of Spring Garden Ranch Road, is needed for roadway resurfacing and to begin transitioning into work on the second half of the roundabout included in this project. No driveways will be impacted by this closure.
The planned detour routes are as follows:
- Motorists traveling east on Spring Garden Ranch Road wishing to travel to U.S. 17 will turn right on Argon Avenue, turn right on E Baxter Street, and then turn right onto U.S. 17.
- Motorists traveling south on U.S. 17 wishing to travel to Spring Garden Ranch Road will turn left on E Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
- Motorists traveling north on U.S. 17 wishing to travel to Spring Garden Ranch Road will turn left on Spring Garden Avenue, turn left on Ponce De Leon Boulevard, turn left on E Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
- Motorists traveling east on Spring Garden Avenue wishing to travel to Spring Garden Ranch Road will turn right on U.S. 17, turn left on E Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
- Motorists traveling south on Ponce De Leon Boulevard wishing to travel to Spring Garden Ranch Road will turn left on East Baxter Street, turn left on Argon Avenue, and then turn left onto Spring Garden Ranch Road.
-
Motorists are advised that a continuous inside lane closure will be implemented northbound U.S.1 (S.R. 5) from Miller Cove Road to south of Pineda Causeway (Castaway Marine Boat Shop).
The closure is necessary for drainage reconstruction.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Motorists are advised that a continuous inside lane closure will be implemented southbound U.S. 1 (S.R. 5) from Old Dixie Highway to Okalani Street.
The closure is necessary for drainage reconstruction.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Motorists are advised that a continuous outside turn lane closure will be implemented southbound S.R. A1A from north of Palm Springs Boulevard to Atlantic Boulevard.
The closure is necessary for drainage reconstruction and miscellaneous construction activities.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Motorists are advised that the Florida Department of Transportation (FDOT) will implement overnight closures of the eastbound State Road (S.R.) 408 off ramp to Conway Road (S.R. 15) (Exit 13), as well as the westbound S.R. 408 on ramp from Conway Road, beginning Sunday, May 18, through Friday, May 23. The closures are necessary for paving operations.
These closures will begin as early as 11 p.m. each night and are scheduled to reopen by 6 a.m. the following morning, with the last closure opening on the morning of Saturday, May 24. This work is part of FDOT’s resurfacing project on Conway Road from Devonshire Lane to Lake Underhill Road.
Detour Information:
- Motorists traveling north on Conway Road who wish to access westbound S.R. 408 should turn left on Lake Underhill Road and continue west to South Street. From there, drivers should head west on South Street to access westbound S.R. 408.
- Alternatively, motorists can head east on Lake Underhill Road, then turn left onto northbound Andes Avenue to access the westbound S.R. 408 entrance ramp.
- Motorists traveling east on S.R. 408 who wish to access Conway Road should exit early at Bumby Avenue (Exit 12A), continue east on Anderson Street, then turn right onto Lake Underhill Road, continuing east to Conway Road.
-
Sunday, May 18 through Friday, May 23 from 11 p.m. to 6 a.m.: Motorists should expect alternating northbound and southbound single lane closures on Conway Road from Curry Ford Road to Lake Underhill Road for paving. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Sunday, May 18 through Friday, May 23 from 11 p.m. to 6 a.m.: Motorists should expect southbound single lane closures on Conway Road from Curry Ford Road to Kasper Drive for mast arm work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Sunday, May 18 through Friday, May 23 from 11 p.m. to 6 a.m.: Motorists should expect westbound On-Ramp detour on the Lake Underhill and Conway Road S.R. 408 entrance for paving and resurfacing. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Sunday, May 18 through Friday, May 23 from 11 p.m. to 6 a.m.: Motorists should expect eastbound Off-Ramp detour on the Lake Underhill and Conway Road S.R. 408 entrance for paving and resurfacing. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Motorists are advised that continuous lane closures will be implemented in the median of South Conway Road (S.R. 15) from Devonshire Lane to Lake Underhill Road. The closure began as early as Monday, April 14, and is expected to remain in place through June 2025.
Northbound and southbound traffic will shift to the outside lanes to provide space for crews working on the median turn lanes and inside lanes. In addition to the lane closure, some side streets will be restricted to right turn only. These include Montclair Road, Rockledge Road, Loring Road, Larado Road, Wayfarer Place, Hargill Drive, and Kasper Drive.
-
Sunday, May 19 to Thursday, May 22 from 8 p.m. to 5 a.m.: Motorists can expect westbound and eastbound alternating lane closures on Silver Star Road from John Young Parkway to Princeton Street for asphalt and paving work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.
-
Motorists are advised that a continuous closure will be implemented on the Western Bascule Bridge (S.R. 401) from southbound S.R. 401 to westbound S.R. 528 starting as early as Thursday, April 3. The closure is expected to remain in place through July 2025.
Southbound S.R. 401 traffic wishing to travel to Westbound S.R. 528 will be directed to the middle bridge on S.R. 401 and use the access road on the west side of S.R. 401 to exit to Westbound S.R. 528 Ramp.
The closure is necessary for the rehabilitation of the bascule bridge, including the replacement of the coating system and machinery. The other two bridges will remain open to accommodate both northbound and southbound traffic. Marine traffic may cause the bridges to close temporarily.
-
Motorists are advised that construction activities are underway along the southbound lanes of Ocean Shore Boulevard between East Granada Boulevard and Standish Drive. This work requires temporary lane closures and detours to safely accommodate drainage improvements, curb and gutter installation, and pedestrian enhancement operations. Beginning as early as Tuesday, April 29, the southbound lanes of Ocean Shore Boulevard between Amsden Road and Neptune Avenue will be closed for approximately three months. This is the second of three non-concurrent detour segments. The closure dates for segment three will be announced at a later date.
Detour maps can be found below under the 'Project Images' section. Please see the anticipated schedule from the Florida Department of Transportation (FDOT) below:
- Segment 1: The southbound lanes of Ocean Shore Boulevard will be closed between Neptune Avenue and East Granada Boulevard for approximately two months. Please note that the detour will be temporarily lifted for Daytona Bike Week and Spring Break from Friday, Feb. 28 through Sunday, Mar. 23. Construction activities will take place in the shoulder behind barrels. Roadway construction activities and the detour will resume on Monday, Mar. 24.
- Detour information: Motorists traveling south on Ocean Shore Boulevard wishing to reach East Granada Boulevard will turn right on Neptune Avenue, turn left on North Halifax Drive, and then continue south to East Granada Boulevard. This segment is complete.
- Segment 2: The southbound lanes of Ocean Shore Boulevard will be closed between Amsden Road and Neptune Avenue for approximately three months. This closure will be in place starting as soon as Wednesday, April 30.
- Detour information: Motorists traveling south on Ocean Shore Boulevard will be directed to turn right on to Amsden Road, turn left onto North Halifax Drive, and then continue south to East Granada Boulevard. From there, motorists can turn left to return to Ocean Shore Boulevard. Daytime flagging operations will be in place at the intersection of Amsden Road and Halifax Drive to facilitate traffic flow.
- Segment 3: The southbound lanes of Ocean Shore Boulevard will be closed between Standish Drive and Amsden Road for approximately two months. The closure dates for this segment will be announced subsequently.
- Detour information: Motorists traveling south on Ocean Shore Boulevard wishing to reach East Granada Boulevard will turn right on Standish Drive, turn left on North Halifax Drive, and then continue south to East Granada Boulevard.
- Segment 1: The southbound lanes of Ocean Shore Boulevard will be closed between Neptune Avenue and East Granada Boulevard for approximately two months. Please note that the detour will be temporarily lifted for Daytona Bike Week and Spring Break from Friday, Feb. 28 through Sunday, Mar. 23. Construction activities will take place in the shoulder behind barrels. Roadway construction activities and the detour will resume on Monday, Mar. 24.
-
May 8-22: (Sunday through Thursday nights), 8 p.m. to 7 a.m.
Northbound I-75 lane closures from C.R. 462 to C.R. 475 are expected to accommodate bridge repair and inspections.
Note: Work will not take place on May 9-10 due to the Rock the Country weekend music festival.
Spring 2025:
Motorists should be advised that nightly lane closures on northbound Interstate 75 (I-75), beginning at the County Road 462 overpass in Sumter County (near Mile Marker 331) and continuing north for approximately 2 miles (near Mile Marker 333).
Nightly single- and double-lane closures are scheduled to start as early as 9 p.m. on Sunday through Thursday nights and continue through 7:30 a.m. the next morning (Monday through Friday).
These lane closures are needed as the Florida Department of Transportation (FDOT) does shoulder work in this section of I-75 northbound.
FDOT advises motorists to reduce their speed, follow all posted signage, and exercise extra caution in the work zone. Delays may occur. Construction schedules are subject to change due to weather or other unforeseen circumstances.
-
Monday, May 19 to Wednesday, May 28: Motorists can expect an outside single lane closure on southbound State Road (S.R.) A1A at the intersection of S.R.A1A and Glenview Boulevard for paver removal.
No expected detours at this time.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Monday, May 19 to Wednesday, May 28: Motorists can expect an outside single lane closure on southbound State Road (S.R.) A1A at the intersection of S.R.A1A and Riverview Boulevard for paver removal.
No expected detours at this time.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Monday, May 5 to Monday, May 19: Motorists can expect inside single lane closures on northbound and southbound State Road (S.R.) A1A at the intersection of S.R.A1A and Glenview Boulevard for paver removal.
No expected detours at this time.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Monday, May 5 to Monday, May 19: Motorists can expect inside single lane closures on northbound and southbound State Road (S.R.) A1A at the intersection of S.R.A1A and Riverview Boulevard for paver removal.
No expected detours at this time.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!
-
Friday, Jan. 31., a traffic shift will be implemented on State Road (S.R.) A1A between Milsap Road and University Boulevard.
This traffic shift will convert the roadway to its final configuration and is expected to remain in place as the Florida Department of Transportation (FDOT) continues work on its project to improve safety and traffic operations in this corridor.
Northbound and southbound traffic has been shifted toward the medians to provide space for crews working in the outside lanes. The center turn lanes within the medians will be maintained.
The speed limit of 35 mph throughout the corridor will be maintained for the duration of the project.
FDOT advises motorists to reduce their speed, follow posted signage, and exercise extra caution in the work zone. Construction schedules are subject to change due to inclement weather or other unforeseen circumstances.
-
May 11-17 and 18-21 (10 p.m. - 5 a.m.)
- Westbound I-4 entrance/exit ramp for Sand Lake Road
-