447118-1 US 1 (SR 5) over Pellicer Creek Bridge Replacement
Project Details
Estimated Costs
| Construction Cost: | $13.9 Million | 
|---|
About
The purpose of the project is to replace the northbound and southbound U.S. 1 (State Road 5) bridges over Pellicer Creek at the Flagler/St Johns County line.
The Project Development and Environment (PD&E) Study was completed in February 2025. The final PD&E Study document is provided below. The project is currently in the design phase.
Contact Information
| Design Project Manager | 
|---|
| 
							
                               Shelley ChinQuee								
 (386) 943-5439 
                                                                        Shelley.ChinQuee@dot.state.fl.us
																		
									
                             | 
                        
| Design Firm | 
| 
							
                               Florida Bridge and Transportation, Inc.								
 |