Project Details
Work Type: Pedestrian Crossing
Phase: Design
Length: 0.1 miles
Design Cost: $101,779.62
Letting: 10/31/2025
Estimated Costs
Construction Cost: $200,000
About

The project at the intersection of US 1 NB and SB Between Palmetto St and Pine St in Tituville is designed to improve overall safety and traffic operations. A traffic services study conducted by the Department determined that a new traffic signal is warranted at this location.

As part of the Traffic Operations Pushbutton Program, the project includes the installation of RRFB. Additional improvements will include speed feedback sign and upgraded intersection lighting to improve visibility and safety within the intersection area.