Project Details
Work Type: Safety Project
Phase: Design
Length: 1.461 miles
Design Cost: $1.4 Million
Letting: 10/28/2026
Estimated Costs
Construction Cost: $5.1 Million
About

The purpose of this project is to enhance safety along State Road (S.R.) 438 (Silver Star Road) between Lake Stanley Road and Lake Hiawassee Road east of Ocoee. Proposed improvements include:

  • Reconstructing the signalized intersections along S.R. 438 at Apopka Vineland Road and at Hiawassee Road to include new "Yield to Pedestrians" signs, special emphasis crosswalks, reconstructed pedestrian curb ramps, and audible pedestrian countdown signals.
  • Providing special emphasis crosswalks and upgraded pedestrian curb ramps at the intersections at Bon Air Drive, Laurel Hill Drive and Renegade Drive. 
  • Creating a signalized restricted crossing intersection with a reconstructed bi-directional median at Silkwood Circle. The reconstructed median will provide a pedestrian refuge, and new special-emphasis crosswalks will be added.
  • Installing new backplates to the traffic signals at Lake Stanley Road and Glen Drive to increase visibility.

Intersections where work is taking place will have the pavement surface replaced to accommodate updated pavement markings.

Contact Information
Design Project Manager
Aleacia Spann
(386) 943-5234
Aleacia.Spann@dot.state.fl.us
Design Firm
Element Engineering group