Project Details
Work Type: Resurfacing
Phase: Construction
Length: 1.443 miles
City:
County:
Road:
Construction Cost: $5.7 Million
Project Start: Late 2024
Est. Completion: Fall 2025
About

The Florida Department of Transportation (FDOT) is installing operational and safety improvements along State Road (S.R.) 416 (Silver Star Road) from S.R. 438 (Princeton Street) to U.S. 441 (Orange Blossom Trail). In addition to repaving the roadway, the project will install a raised traffic separator east of the S.R. 423 (John Young Parkway) intersection. Concrete traffic islands will also be built at Hansrob Road and the Wawa driveway to limit left turns onto Silver Star Road from these locations. Traffic and pedestrian signal upgrades are planned at key intersections, including Princeton Street, Eunice Avenue, and Mercy Drive. The project will improve safety and accessibility by filling sideway gaps for pedestrians, enhancing connectivity along the paved shoulders for bicyclists, installing bus stops, and reconstructing curb ramps to meet current Americans with Disabilities Act (ADA) standards. Lighting improvements at signalized crosswalks, new signage, and pavement markings are also included.

Contact Information
Communications Team
Annabelle Bruzos Vega
(321) 319-8130
Annabelle.BruzosVega@dot.state.fl.us
Lane Closures
  • Thursday, April 3, 2025, from 5:30 p.m. to 5 a.m.: Motorists should expect a right shoulder and full driveway closure on State Road 416, Silver Star Road, about 200 feet west of John Young Parkway. Crews will remove the existing driveway and widen both the roadway and the driveway. The Florida Department of Transportation urges all roadway users to drive, walk and bike with caution and courtesy.

  • Monday, March 31 through Friday, April 4 from 8:30 a.m. to 4 p.m.: Motorists can expect outside westbound turn lane closures S.R. 416 from Mercy Dr. to John Young Parkway for drainage and trench work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 31 through Friday, April 4 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, April 14 through Friday, April 18 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, April 21 through Friday, April 25 from 8:30 a.m. to 4 p.m.: Motorists can expect eastbound outside single lane and right turn lane closures on S.R. 416 from Princeton St to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 31 through Friday, April 4 from 8:30 a.m. to 4:30 p.m.: Motorists can expect alternating eastbound lane shift on S.R. 416 at John Young Parkway to Orange Blossom Trail for sodding and earth work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, April 14 through Friday, April 18 from 8:30 a.m. to 4:30 p.m.: Motorists can expect alternating eastbound lane shifts on S.R. 416 at John Young Parkway to Orange Blossom Trail for sodding and earthwork. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, April 21 through Friday, April 25 from 8:30 a.m. to 4:30 p.m.: Motorists can expect alternating eastbound lane shift on S.R. 416 at John Young Parkway to Orange Blossom Trail for sodding and earth work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, March 31 through Friday, April 4 from 8:30 a.m. to 4:30 p.m.: Motorists can expect alternating eastbound lane shifts on S.R. 416 at John Young Parkway to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, April 14 through Friday, April 18 from 8:30 a.m. to 4:30 p.m.: Motorists can expect alternating eastbound lane shift on S.R. 416 at John Young Parkway to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

  • Monday, April 21 through Friday, April 25 from 8:30 a.m. to 4:30 p.m.: Motorists can expect alternating eastbound lane shift on S.R. 416 at John Young Parkway to Mercy Drive for drainage installation, curb, gutter, and sidewalk work. FDOT encourages all roadway users to drive, walk, and ride with caution and courtesy.

Project Files