Project Details
Work Type: Resurfacing
Phase: Construction
Length: 2.25 miles
City:
County:
Road:
Construction Cost: $5.4 Million
Project Start: Fall 2025
Est. Completion: Early 2027
About

The purpose of the project is to resurface the sections of State Road (S.R.) 434 from Rangeline Road to Milwee Street and from Myrtle Street to west of Talmo Street, with the non-contiguous segment between Milwee and Myrtle Streets addressed separately under Project 439040-1. The project will also upgrade pedestrian curb ramps as needed to comply with current Americans with Disabilities Act (ADA) standards.

Contact Information
Communications Team
Ryan Yglesias
(407) 278-2713
Ryan.Yglesias@dot.state.fl.us
Contractor
Hubbard Construction
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Project Files