Project Details
Work Type: Bridge Work
Phase: Construction
Length: 2 miles
City:
County:
Road:
Construction Cost: $128 Million
Project Start: Late 2021
Est. Completion: Spring 2025
About

The Florida Department of Transportation (FDOT) is replacing the NASA Causeway Bridge over the Indian River to support future growth and improve public and commercial mobility. The current NASA Causeway consists of twin bascule bridges constructed in 1964, which are being replaced with new twin high-level bridges that will provide improved movement for oversized vehicles to launch sites. 

The NASA Causeway Bridge is being reconstructed under a partnership between the FDOT, NASA, and Space Florida. The State of Florida secured a $90 million Infrastructure For Rebuilding America (INFRA) Grant from USDOT. The grant will help to provide part of the funding needs for this bridge project as well as the widening of Space Commerce Way. 

With a taller and wider fixed bridge, spanning 4,025 feet over the Indian River Lagoon and rising 65 feet above the water, the new NASA Causeway Bridge will enhance the accessibility of this corridor, which includes Kennedy Space Center and the Cape Canaveral Spaceport.

In June 2023, the eastbound bridge was opened to the public, a milestone completion for this project. The westbound bridge is currently scheduled to open early spring of 2025.

Contact Information
Communications Team
Ashley Ingham
(321) 634-6111
Ashley.Ingham@dot.state.fl.us
Contractor
Orion Marine Construction, Inc.
Lane Closures
  • 1 a.m. Monday, December 23, through 2 p.m. 

    Motorists can expect single inside lane closures eastbound and westbound along the NASA causeway bridge. These closures are needed for concrete pouring on Pier 24.

     

  • Ongoing Closures to be expected along the existing NASA Causeway

    Motorists can expect lane closures along the NASA Causeway. Traffic will be diverted to the available lanes. 

    This closure is needed to facilitate construction of the new bridge.

    Please proceed with caution in construction zones.