437942-2 US 92 from the Halifax River Bridge to S.R. A1A Landscaping
Project Details
Work Type: | Landscaping |
---|---|
Phase: | Construction |
Length: | 0.682 miles |
City: | |
County: | |
Road: | |
Construction Cost: | $1.6 Million |
Project Start: | Spring 2025 |
Est. Completion: | Summer 2025 |
About
This project involves landscaping International Speedway Boulevard (U.S. 92/S.R. 600) between the Halifax River Bridge and S.R. A1A to enrich the local community with aesthetic upgrades and enhance safety throughout the roadway. This project is following the safety project that was completed in March, 2025 which included widening International Speedway Boulevard (U.S. 92/S.R. 600) between the Halifax River Bridge and S.R. A1A.
Contact Information
Communications Team |
---|
Debbie Cople
(386) 740-3566
Debbie.Cople@dot.state.fl.us
|
Contractor |
Arazoza Brothers Corporation
|
Lane Closures
-
Monday, July 7 to Saturday, July 12, from 7:30 a.m. to 5 p.m.: Motorists can expect intermittent inside single lane closures on westbound and eastbound U.S. 92 from the Halifax River Bridge to State Road (S.R.) A1A for irrigation, large plant installation, and lateral line installation.
No expected detours at this time.
FDOT encourages all roadway users to drive, walk and ride with caution and courtesy!