435859-5 SR 50 from east of the Sumter/Lake County line to CR 33
Project Details
Estimated Costs
ROW Cost: | $50 Million |
---|---|
Construction Cost: | $62 Million |
About
The purpose of this project is to increase capacity and improve safety on the segment of State Road (S.R.) 50 from the Sumter/Lake County line to County Road (C.R.) 33. The project proposes to widen S.R. 50 from two lanes to four lanes.
The right of way acquisition phase for this project is underway and is expected to finish in early 2026.
The project is not yet funded for construction.
Contact Information
Design Firm |
---|
Jacobs Engineering Group
|
Design Project Manager |
Jude Jean-Francois
(386) 943-5487
Jude.Jean-Francois@dot.state.fl.us
|