EMERGENCY INFORMATION FDOT Emergency Travel Alert: For information on the current situation, please visit the following page - Alerts.

Project Details
Work Type: Resurfacing
Phase: Construction
Length: 12.198 miles
City:
County:
Road:
Construction Cost: $14.6 Million
Project Start: Early 2024
Est. Completion: Spring 2025
About

The Florida Department of Transportation (FDOT) will rehabilitate approximately 12 miles of State Road (S.R.) 19 from S.R. 50 to West Oleander Avenue in Lake County, a stretch that connects Groveland to Howey-in-the-Hills.

These improvements will enhance safety and operations for drivers, pedestrians, and bicyclists. In addition to milling and resurfacing the existing roadway, this project will widen S.R. 19 at County Road 478 (Cherry Lake Road) to create a new southbound left turn lane, make drainage adjustments throughout the project, and widen existing shoulders at the U.S. 27 (S.R. 25) off-ramp.

Bicycle lanes will be provided as paved shoulders and five-foot unmarked keyholes will be added to right turn lanes. Sidewalk improvements are planned from South Florida Avenue to East Lakeview Avenue in Howey-in-the-Hills. Sidewalk curb ramps will be reconstructed to comply with the Americans with Disabilities Act (ADA). Bridge safety improvements will be made at the U.S. 27 and Florida Turnpike overpasses.

WHAT TO EXPECT: During construction, motorists should expect both daytime and nighttime intermittent lane closures and possible detours on weekdays and/or weekends. Electronic message boards and other signage will inform travelers and guide them safely through the work zone.

Access to businesses and residences will be maintained. Uneven pavement is a common condition with projects that require temporary asphalt pavement, or resurfacing, as the contractor must put down different layers of asphalt during various phases of construction. Motorists and cyclists should reduce their speed and exercise caution through the work zone. The presence of obstacles related to construction could make cycling difficult. The construction schedule may change due to weather or unexpected conditions.

As part of an adjacent project (448876-1), sidewalk improvements are planned from South Florida Avenue to East Lakeview Avenue in Howey-in-the-Hills.

Contact Information
Communications Team
Joe Callahan
(352) 326-7744 / (352) 620-3020
Joe.Callahan@dot.state.fl.us
Contractor
C. W. Roberts Contracting, Inc.
For Media Inquiries Only
FDOT-D5Comm@dot.state.fl.us
Lane Closures
  • There are no lane closures at this time.
Goes With
Project Files